BurkeCGI_ProjectAward_CobaltDataCenter

Project Description

Client: Cobalt Data Center
Location: Las Vegas, Nevada
Contract Method: Negotiated Cost plus a fee with a GMP

Building Square Footage: 16,000 sq. ft.
Project Duration:
 5 Months
Project Completion: December 2012

Architect: Ethos Three Architecture
Owner: V5 Technologies, LLC

Winner of the 2013 NAIOP Spotlight Award for Industry Impact – Best Redevelopment Project. Tenant Improvement which includes 16,000 sq. ft. of new facility upgrades including new fiber backbones, CRAC units, HVAC upgrades, New roof, Installation of (2) backup generators and NVE improvements over 3 acres. The facility is a Tier 3 Data Center and is the first of its kind in Clark County.

Project Features

Burke_Favicon_BulletPoint_40pxTier 3 Data Center Tenant Improvement

Burke_Favicon_BulletPoint_40pxFacility Upgrades

Burke_Favicon_BulletPoint_40pxEnergy Improvements

Burke_Favicon_BulletPoint_40pxNew Roof